top of page

Work in progress at the new Mechanical Sorting Plant of Alexandroupolis, Greece.

The installation process is about to be completed at the Waste Treatment Plant of Alexandroupolis. SABO's technical crew is in continuous and harmonious cooperation with the engineers of the Contractor MESOGEOS S.A. to ensure the assembly with the rest of operations.


In this project, SABO Environmental undertook the implementation of the technological line of the Mechanical Sorting and Refinery Units. More specifically, the scope of the project includes the design, construction, installation and commissioning of the above units.


The plant will have an annual treatment capacity of around 45,000 tons of waste during a single shift.


bottom of page